Design, construction and management of new methane distribution networks in the approx. 20 municipalities of the Campania region. All the works have been carried out, from the intake cabin to the reduction and measurement on national SNAM methane pipelines with maximum working pressure of 75 bar, to the installation of utility meters. The entire network develops for over 200,000 metres with various operating pressures and diameters.

Timing

Settember 2007 – December 2012