Construction of all civil and electromechanical works for the 39,000,000 Watt wind power park consisting of 17 wind turbines featuring 45-metre long blades. The foundations of the wind turbine generator consist of approx. 650 cubic metres of concrete and 70 tons of iron each. The external cable duct, consisting of three lines with new unipolar cables of 630 square mm extends for approx. 20,000 linear metres, crossing three di¬erent municipalities.

Site

Buccino, Ricigliano, San Gregorio Magno (SA)

Timing

May 2008 – August 2009

Client

Sorgenia Green Power