Construction of all civil and electromechanical works for the 36,000,000 Watt wind power park consisting of 12 wind turbines. Each single foundation of the wind turbine generator consists of approx. 630 cubic metres of concrete and 67 tons of iron. The 45-metre long blades were transported via helicopter with load capacity up to 13 tons.

Site

Municipality of Ricigliano (SA)

Timing

June 2006 – July 2007

Client

Fri-El Green Power